BESS Turnkey Solutions

BESS Turnkey Solutions

From C&I storage to standalone large-scale storage – turnkey from a single source.

01

Product Lines by Voltage Level

Four power classes – from 400 V to 380 kV

C&I storage, 400 V – topology

Tier 1 · 400 V

C&I Storage

50 kW–1 MW · behind the meter · microgrid-compatible

Typical configuration

Power / capacity2 MW / 4,18 MWh
C-rate0,5C
Grid Connection400 V NS

Tier 2 · 10–20 kV

Green BESS – PV & wind retrofit

Typical configuration

Power / capacity2,5 MW / 5 MWh
C-rate0,5C
Grid Connection20 kV

Green BESS, 10–20 kV – topology

Large-scale storage with substation, 20 kV – topology

Tier 3 · 20 kV über Umspannwerk

Large-scale storage with substation connection

Typical configuration

Power / capacity60 MW / 120 MWh
C-rate0,5C
Grid Connection20 kV via substation

Tier 4 · 110 kV / 380 kV

Standalone Large-Scale Storage

Typical configuration

Power / capacity100 MW / 400 MWh
C-rate0,5C
Grid Connection110 kV / 380 kV

Standalone large-scale storage, 110/380 kV – topology

02

Turnkey Process

Five steps to your turnkey storage system

Turnkey process – isometric overview

1

Initial Planning

System configuration, layout, simulation

2

Detailed Engineering

Primary and secondary systems, civil works, BOQ

3

Component Delivery

Procurement and delivery of all components

4

Construction & Installation

Civil and electrical works, installation, cabling

5

Commissioning

System commissioning, tests, certifications

03

Turnkey Process

Project lifecycle: 11–18 months

Phase I

1–2 months

Phase II

3–6 months

Primary bottleneck

Phase III

3–6 months

Phase IV

3–6 months

Phase I – Feasibility & Sizing

FCR/aFRR revenue modeling · P/E sizing · PCS/battery selection

Phase II – Grid Connection & Capacity Management

Capacity sharing · APL · TSO/DSO agreements

Phase III – Detailed Design, Procurement & Permitting

EMS/control design · fire protection · procurement with delivery scheduling

Phase IV – Construction, Commissioning & Acceptance

Civil works & installation · FCR tests · final grid acceptance

04

How Your Storage System Comes Together

The Turnkey Formula

Storage System

Sungrow / CRRC / CATL-NARI

+

Grid Connection

CPS grid connection station or substation

from our business fields

+

Implementation

Construction · Installation · Commissioning · Grid integration

=

Result

Your turnkey storage system